Risk-Based Inspection (RBI) and Norway’s Five-Year STK Rule

The five-year STK rule is an upper limit, not a waiting period. Understand when operating conditions call for earlier inspection ...
five-year-stk-rule-risk-based-inspection
dot
5
(2)

Can systematic condition inspection (STK) intervals exceed five years in Norway?

Short Answer

From 1 January 2027, systematic condition inspection (STK) must be performed at least every five years. A longer interval is permitted only where the equipment or installation belongs to an undertaking subject to the relevant Section 17 consent requirement and inspections follow a risk-based inspection (RBI) programme under a recognised norm. Both conditions must be met. An RBI study alone does not justify extending the interval.

From 1 January 2027, systematic condition inspection (STK), or systematisk tilstandskontroll in Norwegian, must be performed at least every five years under the amended Section 9 of Norway’s hazardous-substances regulation. Frequency and scope must also reflect operating conditions, which may require earlier inspection.

Five years is the ordinary upper limit, not a waiting period. An interval beyond it is available only through the specific Section 17 consent requirement and recognised-norm RBI programme conditions in FOR-2026-02-04-140.

For an overview of the regulatory changes, see Norway’s hazardous substance inspection rule changes from 2027.

Why some installations need shorter intervals

The owner or user must arrange STK to ensure satisfactory technical condition. Setting the next date therefore requires consideration of the installation’s actual service and the evidence from previous inspections.

For example, a change in operating conditions, developing deterioration or incomplete inspection coverage may affect the basis for the existing interval. Their significance needs technical assessment for the installation. The date on an earlier report is only part of that assessment; its scope, findings and limitations also matter.

The STK interval is not every test interval

Section 9 sets the interval for STK as a regulatory activity. It does not place every individual component, test or inspection method on one universal five-year schedule. Supporting examinations and safety-function checks need intervals appropriate to their own applicable requirements and operating context.

The requirement for an accredited body is another question. FOR-2026-02-20-244 confirms the corrected reference to the accredited-body definition for STK of categories a–j. The applicability guide explains those categories. Equipment outside the list may still fall under the broader STK duty.

For information about selecting a provider, see our guide to accredited inspection bodies in Norway and the differences between Types A, B and C.

It is also important to distinguish STK during service from inspection before operation. Our guide to installation inspection versus STK explains the different purposes of these inspection stages.

Two conditions for more than five years

The extension provision applies where both conditions are met:

  1. The equipment or installation is in an undertaking with the relevant requirement for consent under Section 17.
  2. Inspections are carried out in accordance with an RBI programme following a recognised norm.

Section 17 status alone does not justify an extension. An RBI study alone does not make an undertaking eligible. The provision also sets no universal replacement interval: a qualifying installation does not automatically move to ten years.

“Recognised norm” requires an identifiable technical basis suitable for the programme. The wording does not name one commercial method or software product as mandatory. The norm selected and its relevance to the installation should be clear in the programme documentation.

The broader relationship between inspection intervals, accreditation and regulatory applicability is explained in our guide to hazardous substance inspection requirements in Norway.

RBI must lead to inspection work

A generic risk assessment may identify hazards without defining the inspections needed to manage equipment condition. RBI connects the assessment to an inspection programme. Under the extension provision, inspections are performed within that programme; RBI does not replace them.

Four practical questions help assess the basis:

  • Boundary: which equipment and systems are included?
  • Norm: which recognised norm governs the programme?
  • Evidence: what condition data, operating history and uncertainty support its decisions?
  • Implementation: how are inspections carried out, results reviewed and the programme updated?

A suggested interval in a presentation is not the same as an implemented programme. For the supporting records and site arrangements, use the STK inspection preparation guide.

NWE’s risk-based inspection (RBI) service provides engineering support for developing an inspection programme based on equipment condition, deterioration mechanisms and the consequences of failure.

Older undertakings: establish the actual consent position

The amended Section 27 states that the requirement to obtain Section 17 consent applies only to undertakings established after 8 June 2009. This makes the legal position of an older undertaking relevant when assessing the route beyond five years.

Do not infer eligibility from an asset name, its age or a general industry category. Review the undertaking’s establishment, applicable consent requirements, existing decisions and relevant changes. Where the position is unclear, obtain site-specific clarification before relying on an extended interval. A general article cannot establish that status for an individual site.

The Norwegian Directorate for Civil Protection (DSB) provides further information about consent requirements in its official guidance on obtaining consent.

Keep the inspection history across 2027

The commencement date does not restart every installation’s five-year cycle. Build the schedule from its inspection history and the requirements that apply to it. Section 27’s historic twelve-month wording is not a new blanket grace period for the 2027 inspection changes.

Existing DSB thematic guidance contains wording from the earlier regime. It remains useful technical context, while the adopted amended Section 9 controls the 2027 interval rule. DSB has announced new guidance in connection with the amendments.

Document the basis for the chosen interval

NWE’s in-service inspection and RBI engineering are separate deliverables. Any accredited inspection must match the current INSP 073 scope; an engineering recommendation is not regulatory approval of an extension.

The interval record should connect the covered equipment, inspection evidence, operating assumptions and next date. For a period beyond five years, it also needs a clear Section 17 basis and reference to the recognised-norm RBI programme under which inspections are performed. Until those conditions are established, the proposed extension remains unresolved.

How useful was this post?

Click on a star to rate it!

5 / 5. 2

Saeed Ebrahimi
NWE Leadership

Saeed Ebrahimi

CEO · NWE Group

Saeed Ebrahimi is the CEO of NWE Group, combining hands-on technical inspection experience with executive leadership across inspection, quality, project delivery and international business.

Focus: Vendor Inspection · Quality Surveillance · Subsea Inspection · Welding Engineering · NDT · International Projects

Leave a Reply

Your email address will not be published. Required fields are marked *

ON THIS PAGE
Table of Contents

Have a project requirement?
Need independent inspection or engineering support for an upcoming or ongoing project?